Equipment problems delay arrival of renourishment work on beach by Ocean Lakes
Equipment problems have stalled progress on beach
renourishment work this week, delaying its arrival on the beach by Ocean Lakes
Family Campground.
Crews finished repairing offshore equipment and got sand pumping to the beach again Friday morning after a week of delays. The work
is expected to reach the beach by Ocean Lakes on Sunday or Monday, barring any additional mechanical or weather delays.
Crews work Friday morning to repair the booster pump used to get sand to the beach for renourishment. Mechanical problems with the boosters have delayed progress up the beach this week. |
Crews have been stuck in the same spot just south of the
Holiday Inn Oceanfront at Surfside Beach most of the week because of equipment problems with the
offshore boosters.
The renourishment work stalled just south of the Holiday Inn Oceanfront at Surfside Beach this week. Crews resumed renourishment work Friday. |
The boosters pump sand to the beach, where crews use heavy equipment to spread the sand to build up the beaches, which have been battered by hurricanes, most recently Hurricane Matthew in October.
The schedule depends on a number of factors, including weather and equipment issues, and can change at any moment.
Until the delays this week, crews had been steadily progressing up the beach since
beginning the $26.3 million renourishment project just north of the SurfsideBeach Pier in July.
It will take about 10 to 14 days to complete the nearly
mile-long stretch of beach by Ocean Lakes, barring any weather or mechanical
delays.
Beach-goers can track the progress with the real-time onlinemap.
Will I still have access to the beach?
Yes. Crews are blocking off 1,000-foot sections
of beach at a time for the work and anticipate each section will be closed
about two or three days.
The beach by Ocean Lakes stretches nearly 5,000
feet, so guests still will have access to the majority of the beach by Ocean
Lakes at any given time during the work – it just may not be their usual
favorite spot on the beach.
How noisy will the work be?
Crews plan to work 24 hours a day, seven
days a week to finish the project as quickly as possible. There will be noise from the bulldozers, front-end
loaders and other equipment, including the back-up alarms that are required by
federal law and cannot be shut off.
Why are you doing this work during the peak
beach season? Couldn’t you wait until the fall?
The U.S. Army Corps of Engineers set the timing
for this project; it was beyond Ocean Lakes’ control.
Corps officials said the money for the project
came through emergency funds, which have to be spent as soon as possible. Also,
there was a short window this summer when the equipment needed for this project
was available.
The renourishment work is
crucial to rebuild the beach and dunes, which help protect the area from
storms. Hurricane Matthew in October wiped out our dunes and battered our
beaches.
“Beginning
the construction project now enables the major, long-term benefits of
protecting people and property from storm damage to be realized as soon as possible
and before peak hurricane season,” said Glenn Jeffries, spokeswoman for the
U.S. Army Corps of Engineers in Charleston.
Is there
a way to know where crews are working before I head to the beach each day?
Yes. Beach-goers can track the progress on a real-time map to see
where the work is taking place.
How long
will crews be working on the beach by Ocean Lakes?
Crews will work in 1,000-foot
sections and are expected to complete about 500 feet a day. It will take crews
about 10 to 14 days to complete the stretch of beach by Ocean Lakes, barring any mechanical or weather delays. At any given time, the majority of the beach will be open and available to
beach-goers.
What’s the deal with this pipe running along
the ocean?
The pipe runs up the beach
outside of the blocked-off work area and is used to pump the sand onto the
beach.
Please do not sit on the pipe
or try to climb over it. Use the sand ramps over them to cross safely.
We thank all of our guests for their patience and cooperation during this
much-needed work. Enjoy your stay with us!
Use the sand ramps to cross the pipe on the beach. |